Over the years the number of connections has grown: Startup Nov 1974 – 24 connected. November of 1975, one year later – 50 connected. Fifteen years later in 1990 – … Continue reading
Over the years the number of connections has grown: Startup Nov 1974 – 24 connected. November of 1975, one year later – 50 connected. Fifteen years later in 1990 – … Continue reading
As of December 2010 the Woodridge Lake Sewer district Sewer Authority is still operating under the conditions of the consent order. Since the consent order was issued the district has … Continue reading
On March 25, 2010 the then-current engineering consultant emailed the DEP and attached a draft scope of a wastewater facility plan and time schedule that his office prepared for the … Continue reading
On November 25, 2009 the DEP responded by letter stating that it indicated in its December 2002 letter its reluctance to favorably review the nonpoint source discharge option (lateral gravel … Continue reading
On October 7, 2009 the district responded by a letter outlining the engineering studies done from 1993-1995 that concluded with two alternatives: an upgraded plant with lateral gravel filters as … Continue reading
On July 20, 2009 the DEP wrote the district requesting a written response by October 2009 as to how the district planned to comply with its conditions for sewer operations … Continue reading
On May 6, 2009 the DEP issued a Notice of Violation to the district that it was operating without a Class III Operator required in a Class III Facility which … Continue reading
On July 6, 2005 the Torrington Water Pollution Control Authority (WPCA) sent a detailed response to the DEP raising a number of questions with the district’s scope of the study. … Continue reading
Continuing to work with the DEP in February 2005 the district submitted a detailed scope of study to the DEP that outlined two core alternatives: (1) Upgrade the existing WLSD … Continue reading
On July 8, 1996 the DEP issued an approval relating to a hydraulic study required by the July 1989 consent order. It included conditions requiring more detailed engineering studies by … Continue reading